The latest project update from Julie Ebersole, Park Manager, Phoenix Parks and Recreation Department, Downtown Division. (images included in the attachment)
Encanto Park Improvement Project Summary
Below is a summary of the projects that are currently underway at Encanto Park. The order of the projects listed is based on priority and projected construction completion dates from the Parks Division and community input.
1. Sports Complex
The Sports Complex has been open for use. There are minor repairs taking place that remain from the contractor’s punchlist.
2. Perimeter Fence Project
The perimeter fence is complete. The contractor is still cleaning in a few areas to complete comply with all contract obligations.
3. Restroom Buildings
Plans are 100% complete and have been permitted.
4. Picnic Areas
The ramada plans are 100% complete and have been permitted.
5. Lake Improvements
Pump is complete.
6. Signage and Entrance Enhancements
Plans are 100% complete and have been permitted.
7. Playgrounds
Now that the Sports Complex and the fence projects are completed, the playground project will take the forefront and be one of the next improvements in the park.
Additional projects as funding permits are: parking lot improvement, lagoon dredging, lighting, clubhouse renovation, irrigation improvements, and sports field improvements.
Tags: Encanto, Initiative, PPPI, Park, Parks, Phoenix, Preserve, and, city, of, More…phoenix
Started by Michael Puceloski. Last reply by Kelly Larabee Feb 13, 2019.
Started by Kelly Larabee Feb 5, 2018.
© 2024 Created by Kelly Larabee. Powered by